SRP Santan Generating Station
- 8 Economizer Headers
- 8 Evaporator Headers
- 8 Superheater Headers
APS West Phoenix Power Plant
- 6 Economizer Headers
- 4 Evaporator Headers
- 4 Superheater Headers
APS Red Hawk Power Plant
- 2 Reheat Headers
|
|
IVRC Power Plant
- 6 Waterwall Panels
Colmac Energy
- 6 Waterwall Panels
SRP Desert Basin
- 4,000 ft Boiler Feed Water Piping
SRP Navajo Generating Plant
- 2 Stainless Steel Tanks
|
| |
|
|
SRP Santan Generating Station
- Replace De-Superheater
- Repair Unit 5A Nozzle
- Repair Unit 5B Nozzle
- Replace De-Superheater Seal Steam
APS West Phoenix Power Plant
- Replace 2 Main Steam Stop Valves
Gila River Power Plant
- Replace Main Steam Valve on Unit 1
14" x Sch 160
APS Red Hawk Power Plant
- 4 Superheater Outlet Headers
- 4 Superheater Inlet Headers
|
|
Mesquite Power Plant
- Fix Tube Leak Unit 2 HPSH - 3"
- Repair Vent Line Unit 6 HPSH - 1"
- Replace Unit 5 HPSH - 2- 3" Bypass Line
- Fix Tube Leak Unit 5 HPSH - 3"
- Repair Unit 6 HPSH - 2" Vent Piping
- Fix Tube Leaks on Unit 2 HPSH - 3" Lower Header
- Fix Tube Leak on Unit 5 HPSH - 3"
- Replace Unit 6 HPSH 3" Riser Elbow 10" x Sch 160
- Replace 2 Unit 5 Attemperator Flanges 3" x Sch 160
- Installed fittings on double block valves for
HPSH - 1" 4 Units
- Installed Hydro Connection for HPSH 2" 4 Units
- Installed Thermal Well on Unit 6 HPSH 3"
|
| Note: Steam Generation performs Brinell testing before welding and after PWHT for additional QA/QC hardness. |